Oct 27, 2015
Howdy, We just wanted to let everyone know that SAMBA volunteers have finished clearing the corridor for the proposed route in Harrisburg! We started on August 4 and worked every Saturday except for one day cancelled due to heavy rain. Thanks to everyone for their...
Oct 22, 2015
Howdy, We continue to clear trail corridor for our proposed route in the Paxtang Parkway this Saturday.We’ll work from 9-1 as usual and hopefully push through the last section of corridor that needs trimmed. We plan to start sculpting trail tread in the next 2...
Oct 15, 2015
Work continues this Saturday from 9-1. We are 75% finished with clearing the corridor. Hope to see you out there!!! OCTOBER 24-MEET @ GREENBELT PARKING LOT – Behind City line diner 3302 Derry St....
Oct 4, 2015
Howdy SAMBA, We are beginning work on the Parkway Trail System in Harrisburg this weekend! Work days are scheduled every Saturday going forward with the goal of having trails open for use this Fall. The first steps will be simply clearing the trail corridor. All work...
Oct 2, 2015
Howdy, Unfortunately Mother Nature is being difficult this week. Trail work is cancelled for this Saturday due to heavy rain. Hope to see you next Saturday!!
Sep 21, 2015
Howdy, UPDATE: We have almost finished brush cutting and corridor clearing in the Cameron Parkway and will be moving on to the Paxtang Parkway this week. Major thanks to our volunteers especially folks like Joe K, Mike S. and Tim F. for their tireless work. Please...